Parking lot update

Our parking lot has had a large section excavated and patched and another smaller area also patched. To ensure that the area solidifies properly the parking lot will remain closed again on Wed. Nov. 4th for one more day.

Our playground area has been completely excavated but there is a great deal of moisture in the sand/gravel mix. Therefore this area needs more time to solidify and will be paved on November 16-17. During these two days the south lot will be open but we ask that drivers be aware that some large trucks will be moving in and out of the west part of the lot and driveway throughout these two days.

Students will be able to access the back field from November 4-13 but are asked to stay off the playground area as much as possible. They will have no access to the back on November 16-17, but should have full access to the back most likely by November 18th or potentially November 19th.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s